Lake City Way Corridor Improvement Project

Updated: March 17, 2021

What’s happening now?

There is an ongoing general strike of concrete drivers and concrete plant workers in the Seattle area that involves companies that supply us with concrete for our many active construction projects.  The strike has impacted this project and caused delays for the concrete work.

This is a challenge and SDOT supports a fair resolution among the parties. In the near term, we're continuing other project work at the site and behind the scenes and will be sure to share more about the strike outcome and any impacts to this project as information becomes available. SDOT remains hopeful that this issue will be resolved soon. Most of the paving portion of this project has been completed by WSDOT with a few portions still remaining between NE 90th St and NE 95th St.  In February, temporary stripes were painted on Lake City Way NE and crews will return as early as May  to complete the permanent striping.  There are also segments of sidewalk and driveways that still need to be completed along the corridor. 

Here is the status of the four intersection improvements led by SDOT:

Lake City Way NE and NE 137th St

  • Sidewalk and new curb ramps have been completed
  • Currently working on the SE corner Lake City Way NE and NE 135th St
  • Sidewalk and new curb ramps have been completed
  • The underground work for new traffic signal has been completed
  • New light pole and traffic signal has been installed. 

Lake City Way NE and NE 95th St

  • Finalizing  work on the NE corner and installing underground electrical conduit for the new traffic signal
  • New traffic signal foundation at the NE corner
  • Remaining sidewalk, curb ramps and new retaining wall on the west side along the Lake City Way has been completed. 

Lake City Way NE and NE 82nd St

  • Underground electrical conduit work for the area has been completed
  • New sidewalk and curb ramps have been completed
  • Temporary  crosswalk striping has been installed.

New crossing signal, crosswalk, curb ramps, and curb bulbs at Lake City Way NE and NE 82nd St

New crossing signal, crosswalk, curb ramps, and curb bulbs at Lake City Way NE and NE 82nd St

New pedestrian signal, crosswalk, curb ramps, and median at Lake City Way NE and NE 135th St

New pedestrian signal, crosswalk, curb ramps, and median at Lake City Way NE and NE 135th St

The best way to stay informed during construction is to sign up for email updates through WSDOT's project webpage.  You can also reach out directly to WSDOT's communications staff for the project, Tom Black: BlackTo@wsdot.wa.gov or (206) 440-4699

Project Overview

Construction began in June 2020 on the Lake City Way paving project which is being led by the Washington State Department of Transportation (WSDOT).  The 4 intersection improvements that we (SDOT) designed will be constructed by WSDOT as part of their paving project. Lake City Way NE (State Route 522) is one of the busiest arterial routes in Northeast Seattle. The 3.67-mile-long corridor (from I-5 to the city limits at NE 145th St) has seen a high volume of collisions over the years. The roadway facilitates travel to and from the city, supports thriving businesses, hosts frequent transit routes, and functions as "Main Street" for residents in this part of the city.

We're working closely with the Washington State Department of Transportation (WSDOT) to enhance safety, accessibility, and travel on Lake City Way NE. WSDOT plans to repave the corridor and upgrade ADA curb ramps where necessary, and we will construct spot and intersection improvements to enhance walkability and safety for all travelers.

Project Design

In 2013 we launched a collaborative process with residents, community groups, Seattle Police, State Patrol, Liquor Control Board, Public Health, WSDOT, and the Washington State Transportation Commission (WSTC), to review street conditions on Lake City Way NE. The collaboration was known as the Lake City Way Traffic Safety Project Task Force. As part of this work, we hosted public events, went door-to-door to local businesses, spoke with neighbors, gathered community input, and discussed strategies to improve safety and mobility along the corridor.

We’ve used this feedback in addition to collision and speed data to inform our design of these intersection improvements.

Project Map

Project area map

Click to enlarge

Proposed improvements at Lake City Way NE & NE 137th St

Lake City Way NE & NE 137th St

graphic overhead map of the improvements at 135th St

Lake City Way NE & NE 135th St

graphic overhead map of improvements at Northeast 95th St

Lake City Way NE & NE 95th St

Proposed improvements at Lake City Way NE & NE 82nd St

Lake City Way NE & NE 82nd St

Outreach & Schedule

We held two public meetings in September 2018 to provide an opportunity for Seattle residents to ask questions, engage with our project team, and learn more about our proposed improvements. For a summary of the comments we heard, please see our outreach summary.

In 2019  we  worked with neighborhood groups, community members, and businesses in the project area to answer questions and provide information about project design and schedule.

The design for the Lake City Way Corridor Improvement Project was complete in early 2020 and construction began in June 2020.  . Due to the fact that this is a WSDOT let project, the best way to stay informed and receive the latest updates is to sign up for their email updates through their project webpage

Project Budget & Funding

This project is a joint effort between WSDOT and SDOT.

WSDOT funding is provided by Washington State and Federal funds.

SDOT funding for spot and intersection improvements is provided by the 9-year Levy to Move Seattle, approved by voters in 2015.

Materials