30th Ave NE Sidewalk & Natural Drainage System
This project is complete!
Project Overview
Phase One: NE 130th St to NE 137th St
In the spring of 2019 the Seattle Department of Transportation (SDOT) and Seattle Public Utilities (SPU) completed the first phase of new sidewalks and a Natural Drainage System (NDS) along the east side of 30th Ave NE between NE 130th St and NE 137th, making it safer, easier, and more pleasant to walk along 30th Ave NE. The NDS helps capture and treat polluted stormwater runoff before it reaches Thornton Creek, which improves water quality and reduces pollution in Lake Washington. The NDS was designed, constructed, and will be maintained by SPU.
This project was selected as part of our Sidewalk Development Program and as part of SPU’s Integrated Plan to treat polluted stormwater within Thornton Creek Basin. The project captures efficiencies in design and construction, and fosters improved coordination between City departments and their individual projects.
Before and after sidewalk construction along 30th Ave NE
Phase Two: NE 137th St to NE 143rd St
We heard from neighbors during early outreach that the new sidewalks completed in Phase One should be extended north towards N 145th St and we are now making those improvements as a part of Phase Two. To begin creating a clear walking path along 30th Ave NE, we have completed interim improvements between NE 137th and NE 143rd St. The improvements included new gravel, vegetation clearing, and parking restrictions. Full concrete sidewalks will be constructed next as the final part of this work. Natural Drainage Systems will not be a part of Phase Two.
Existing gravel shoulder where we'll build the new sidewalk
Natural Drainage Systems
Natural drainage systems (NDS) are a type of green stormwater infrastructure system (GSI) built to capture runoff and filter pollutants. An NDS uses specialized plant species and soils to filter stormwater runoff and pollutants. Plants are selected to help the NDS do its job: clean stormwater and allow it to slowly seep into the ground.
You can view the plants selected for the NDS on 30th in our “planting palette” located in the materials section of this page.
The image below shows an example cross section of the new sidewalk and natural drainage system. The project design may include elements shown in the cross section and varies by location.
Schedule
June 2020 - early 2021
Phase two of sidewalk construction
July - October 2018
Phase one of corridor wide improvements
January 2018
Designs completed
Completed designs shared with community
September 2017
Begin working with residents about property impacts
July 2017
Designs shared with Lake City Way Neighborhood Alliance
March 2017 - Spring 2018
Finalize project design, community feedback and engagement
March 2017
Early outreach begins
Project Budget & Funding
This project is a partnership between SDOT and SPU.
SDOT funding is through our Sidewalk Development Program, with funds from the Levy to Move Seattle. The 9-year $930 million Levy to Move Seattle was approved by voters in 2015.
SPU funds are from the NDS Partnering Program, which is part of the Plan to Protect Seattle's Waterways and uses NDS to improve water quality in large creek watersheds.
Materials
- Construction Flyer (June 2020)
- Construction Flyer (July 2018)
- NDS Planting Palette (July 2018)
- Project Factsheet (July 2018)
- Construction Flyer (July 2018)
- Construction Staging Flyer (July 2018)
- Project Update Mailer (July 2017)
- Project Factsheet (March 2017)
- Project Update Mailer (February 2017)
- Lake City Greenways Meeting Presentation (March 2017)
- Lake City Greenways Meeting Follow Up: Questions Answered (April 2017)