Project Complete
This project was completed in 2022.
SW Barton St Pedestrian Safety Enhancements
Updated: December 19, 2023
This project was completed in 2022.Thank you to all who participated in the community prioritization process for this Neighborhood Street Fund project. We completed this community-requested project in 2022!
Project Overview
Elements
-
New curb ramps and crosswalks at the intersections of SW Barton St & 25th Ave S and SW Barton St & 24th Ave SW.
-
New left turn arrows for eastbound and westbound movements at SW Barton St and 26th Ave SW to separate pedestrian movements from left turning vehicles.
-
Install new pedestrian activated flashing beacon at the intersection of SW Barton St and 25th Ave SW.
- Upgrade existing signal at SW Barton St and 26th Ave SW.
Benefits
-
Enhanced safety for people crossing the intersections of SW Barton St and 26th Ave SW, 25th Ave S, and 24th Ave SW.
-
Enhanced accessibility for people using mobility devices, riding bikes, or pushing strollers.
-
Increased visibility of transit travelers.
Design
Schedule
The NSF program runs on 3-year cycles to select, design, and build projects. The application phase for the 2019-2021 cycle opened October 2018 and projects will be constructed in 2021.
Phase | Timeline |
---|---|
Applications | 2018 |
Community Prioritization and Voting | 2019 |
Design | 2020 |
Construction | 2021-2022 |
Project Background
This is one of 15 Neighborhood Street Fund projects requested by neighbors and selected by the Levy to Move Seattle Oversight Committee. Neighborhood Street Fund is a city program, running on 3-year cycles, that enables neighbors to propose and help prioritize transportation-related projects that are then built by the Seattle Department of Transportation (SDOT).
Questions?