McGraw St Bridge Seismic Project

Updated: September 27, 2024

What's happening now?

We’ve completed work on seismic retrofits to help the McGraw St Bridge better withstand earthquakes! The bridge has been reopened for people walking, biking, rolling, and driving. Over the past 9 months, we: 

  • Installed carbon fiber wrapping to strengthen the bridge's crossbeams, columns, and arches
  • Strengthened the existing arch with a concrete infill wall
  • Installed concrete blocks and supportive shells for the bridge's columns and crossbeams
  • Repaired cracks and damaged concrete
  • Replaced the expansion joints at both ends of the bridge 

Thank you for helping us improve the resiliency of the McGraw St Bridge! If you have any remaining questions or concerns about the McGraw St Bridge Seismic project, please contact us at 206-684-ROAD (7623) or 684-Road@seattle.gov
 

Project Overview

Click on map to explore it as an accessible PDF.

Earthquakes could have a major impact on Seattle's bridges. To address this risk, the City of Seattle established a bridge seismic program to assess how vulnerable the City's bridges were to earthquakes, and reinforce bridges to better withstand the potential impacts of an earthquake.  

As part of the Levy to Move Seattle, 16 bridges were selected for seismic reinforcement, including the McGraw St Bridge. The McGraw St Bridge is located in the Queen Anne neighborhood, between 2nd Ave N and Nob Hill Ave N. It is an older bridge constructed in 1936 and does not meet current seismic design standards for bridges. The bridge spans the Wolf Creek Ravine Natural Area, and it is used by people driving, biking, walking, and rolling.  

The seismic retrofits to the McGraw St Bridge included several modifications to the existing bridge components to make the bridge less vulnerable in the event of an earthquake. The following were major construction elements:  

  • Installed carbon fiber wrapping to strengthen the bridge's crossbeams, columns, and arches
  • Strengtheneds the existing arch with a concrete infill wall
  • Installed concrete blocks and supportive shells for the bridge's columns and crossbeams
  • Repaired cracks and damaged concrete Replaced the expansion joints at both ends of the bridge  

Schedule

  30% Design   Complete
  60% Design   Complete
  90% Design   Complete
  Construction begins   January 2024
  Retrofit complete   September 2024

Funding

The total project estimate was $7.5 million, and it was funded through the Levy to Move Seattle. Approved by voters in 2015, the 9-year, $930 million Levy to Move Seattle provides funding to improve safety for all travelers, maintain our streets and bridges, and invest in reliable, affordable travel options for a growing city. 

Materials

Translation and interpretation 

If you need this information translated, please call (206) 775-8734.

如果您需要此信息翻譯成中文 請致電 (206) 775-8734.

Kung kailangan mo ang impormasyon na ito na nakasalin sa Tagalog mangyari lamang na tumawag sa (206) 775-8734.

Si necesita traducir esta información al español, llame al (206) 775-8734.

Odeeffannoon kun akka siif (206) 775-8734.

Nếu quý vị cần thông tin này chuyển ngữ sang tiếng Việt xin gọi (206) 775-8734.

የዚህን መረጃ ትርጉም ከፈለጉ፣ በዚህ ስልክ ቁጥር ይደውሉ፡ (206) 775-8734.

ናይዚ ሓበሬታ ትርጉም እንተደሊኹም፣ በዚ ቁጽሪ ስልኪ ይድውሉ፡ (206) 775-8734.

당신이 번역이 정보를 필요로하는 경우에, (206) 775-8734? 전화 해주십시오.

Transportation

Greg Spotts, Director
Address: 700 5th Ave, Suite 3800, Seattle, WA, 98104
Mailing Address: PO Box 34996, Seattle, WA, 98124-4996
Phone: (206) 684-7623
684-Road@seattle.gov

Newsletter Updates

Subscribe

Sign up for the latest updates from Transportation

The Seattle Department of Transportation (SDOT) is on a mission to deliver a transportation system that provides safe and affordable access to places and opportunities for everyone as we work to achieve our vision of Seattle as a thriving, equitable community powered by dependable transportation.