Morgan Junction Park Addition

Updated: January 13, 2025

Early 2025

Work on removing the hazardous soil from the new parcel, formerly used as a dry cleaner, began in 2024. This work included demolition of the existing concrete and asphalt, installation of temporary shoring, and excavation to remove the lens of dry-cleaning solvents. Clean fill is being imported, to be followed by topsoil, temporary irrigation, and grass. Currently, the team is working through some new permitting issues before project phase completion. 

The design and permitting work for the addition project continues. Seattle Parks and Recreation (SPR) is working with community partner Morgan Junction All Wheels Association (MJAWA) to integrate an all-wheels skate-dot into the project. MJAWA working with Grindline Skateparks has gathered community input on potential designs. SPR and MJAWA will work towards integrating the skate-dot into the larger project for permitting and construction.  

To learn more about the Morgan Junction All Wheels Association please visit: https://mjawa.org/

Location

The addition parcel is located at 6317 California Ave SW, adjacent to:
Morgan Junction Park, 6413 California Ave SW, 98136

Budget

The Seattle Park District provides $1,260,000 for the planning, design and construction of the future park. 

Schedule

Anticipated Soil Remediation

Permit & Design: 2025, additional permitting ongoing 
Anticipated remediation complete: Early 2025

Anticipated Park Addition

Permit & Design: Spring 2025 
Bid: 
Summer 2025 
Anticipated Construction:
Summer 2025 - Spring 2026

Project Description

In 2014, Seattle Parks and Recreation purchased the .47-acre property at 6311 California Ave SW, north of Morgan Junction Park, to expand the park and provide additional open space for this high-density neighborhood. The design will incorporate accessibility in compliance with the Americans with Disabilities Act (ADA) and additional park elements will be incorporated after gathering public input.

The additional parcel will not be accessible during construction.

Community Participation

Involvement Opportunity at Morgan Junction Festival - 6/18/2023

Public Meeting and Open House - 6/22/2019

Public Meeting and Open House - 6/16/2018

Seattle Parks and Recreation (SPR) has determined that the project has no probable significant adverse impact on the environment. An environmental impact statement (EIS) is not required under RCW 43.21C.030(2)(c). This decision was made after a review of a completed environmental checklist and other information on file with SPR. This information is available to the public on request. The Determination of Non-Significance was issued on February 22, 2021.

Parks and Recreation

AP Diaz, Superintendent
Mailing Address: 100 Dexter Ave N, Seattle, WA, 98109
Phone: (206) 684-4075
Fax: (206) 615-1813
pks_info@seattle.gov

Newsletter Updates

Subscribe

Sign up for the latest updates from Parks and Recreation

Healthy People, Thriving Environment, Vibrant Community