Lincoln Park South Play Area Renovation
Updated: February 10, 2022
Spring 2022
This project has experienced some unforeseen delays; however, construction documents are in progress. We anticipate the bid advertisement in late spring 2022, with construction starting in summer 2022.
Location
Lincoln Park, 8011 Fauntleroy Way SW, 98136
Budget
Seattle Park District provides $600,000 for planning, design and construction.
Schedule
Design: Spring 2021 - Spring 2022
Bid Advertisement: Spring 2022
Construction: Summer 2022
Project Description
This improvement project is funded by the Seattle Park District. The play area renovation will update play equipment with play structures accessible to children of all ages and abilities. Additionally, accessibility improvements that meet the standards from the Americans with Disabilities Act (ADA) will be made throughout the play area.
Community Participation
Public Meeting 11/29/2017
Public Meeting 1/24/2018