Project overview

Earthquakes could have a detrimental effect on Seattle's infrastructure. To address seismic risks to city infrastructure, the City of Seattle established a bridge seismic retrofit program to assess the seismic vulnerability of the City's bridges and to prioritize limited funding to reduce this transportation infrastructure vulnerability. 

As part of the Levy to Move Seattle, 16 bridges were selected for seismic retrofits, including the 8th Ave NW Bridge. The 8th Ave NW Bridge is an older bridge constructed in 1950 prior to the modernization of the seismic design code. Spanning a forested ravine and connecting different parts of the Broadview neighborhood, it carries both vehicular and pedestrian traffic. 

The planned seismic retrofits to the 8th Ave NW Bridge include several modifications to seismically strengthen existing bridge components and reduce the bridge's vulnerability to earthquakes. There will be construction equipment, noise, dust, and possible detours for the duration of the project to maintain a safe separation between people and the work site. 

Project Map

Map of 8th Ave NW Bridge

Schedule and construction

  • 30% Design - Complete
  • 60% Design - Complete
  • Final Design - Complete
  • Construction begins - January 2022
  • Construction ends - June 2022

Funding

The total project estimate is $3 million and is currently funded by a FEMA grant and through the Levy to Move Seattle. Approved by voters in 2015, the 9-year, $930 million Levy to Move Seattle provides funding to improve safety for all travelers, maintain our streets and bridges, and invest in reliable, affordable travel options for a growing city.

Materials

Transportation

Greg Spotts, Director
Address: 700 5th Ave, Suite 3800, Seattle, WA, 98104
Mailing Address: PO Box 34996, Seattle, WA, 98124-4996
Phone: (206) 684-7623
684-Road@seattle.gov

Newsletter Updates

Subscribe

Sign up for the latest updates from Transportation

The Seattle Department of Transportation (SDOT) is on a mission to deliver a transportation system that provides safe and affordable access to places and opportunities for everyone as we work to achieve our vision of Seattle as a thriving, equitable community powered by dependable transportation.